Kalamunda Library: Solar Panel Installation

Project Status : Complete
Estimated Completion Date : 2 July 2021
Location : 7 Williams Street, Kalamunda

Allocated Budget: $31,000
Works are scheduled to commence Monday, 28 June 2021.

These works are estimated to take five (5) days to complete.  This time-frame may vary slightly due to weather conditions and contractor availability.

All practical efforts will be made to minimise any inconveniences to library users, however, residents and library users are warned to expect some noise disruption during this period. 

All Library Services including our online services will remain in operation during period. The City’s other three libraries will be open as usual.
View location and opening hours here

Please contact the City of Kalamunda via the details provided below with any project related matters including complaints or compliments. 

Project Images

An aerial view for the installation of solar panels Kalamunda Libraries in June/July 2021

Related Documents

No documents attached

Contact Information

Kalamunda Library
Phone: (08) 9257 9999
Email: enquiries@kalamunda.wa.gov.au 

 

© City of Kalamunda 2024