The City of Kalamunda will be upgrading road surfaces on Gotha Way, from Harfield Rd to Abercorn Rd.
This is a two-part project which includes kerb and drainage side entry replacements, and road resurfacing.
Kerb and drainage side entry replacements, will commence first in late-February 2024 and is anticipated to take two weeks to complete. This is dependent on contractor availability and weather conditions.
The road resurfacing is scheduled for early-April 2024.
Properties located adjacent to the proposed works may experience some disruption in relation to exiting and entering the property during kerb replacements. If this situation should occur, then you are requested to contact the City’s kerb contractor1, in the first instance, who will then make the appropriate arrangements with you.
Please be assured that every effort will be made during these works to minimise impact on those who live nearby and also to the environment.
If you have any queries regarding this matter, please call 9257 9999 to discuss.
1 Contractor contact details were provided as part of the notification letters sent to the properties in the work-related area.
Temporary road closure on Gotha Wy and Abercorn Rd. Detours in place via Sussex Rd, Northumberland Rd, Harewood St, Cowra St and Connaught St. Commencing 09 May, from 7:00am – 7:00pm. With contingency dates for 16/05, 23/05 and 30/05.
Road surface works will commence early-May 2024 and is anticipated to take one week to complete. This is dependent on contractor availability and weather conditions.
Road surface works will commence late-April 2024 and is anticipated to take one week to complete. This is dependent on contractor availability and weather conditions.